EES PROJECT: Vicars Oil, Leeds (Phases 1 & 2)
Client:
Britcon (UK) Ltd
Value:
£890,000
Facilities:
Vickers Oil is a family run company which has been resident in Leeds for almost 140 years. They are a Worldwide market leader in the marine, textile and food grade manufacturing markets.
Brief:
We were proud to work alongside principal contractors, Briton (UK) Ltd, for the installation of a new complex laboratory and testing facility which was part of a large £3m expansion project.
The work involved a new extension to an existing office and warehouse, creating a new loading area, office space, laboratories and a new rooftop plant.
Services installed were as follows:
- Fire Alarm
- Intruder Alarm
- TV
- Data
- Intelligent DALI Lighting and Small Power
- Virtual Routing & Forwarding Interface (VRF)
- Ventilation & Air Handling Unit Plant (AHU)
- Gas
- Building Management System (BMS)
- Specialised Laboratory BMS
- Sanitary ware
- Domestic water services
- Public Health Services
- Thermal Insulation
- Test & Commission
Unique Aspects:
Integrating specialist laboratory technology into the Buildings Management Systems
Notable Achievements:
The project was finished in 2019 and completed within the agreed timescale of 10 months.
Due to the complex nature of the build we established a close working relationship with the management at Vickers Oil having negotiated Phase 3 works and ultimately awarded the Service and Maintenance contract through our colleagues at EMS
Professional Team:
WSP
- Client Britcon (UK) Ltd
- Date 26th June 2019